NE Times
UK News

HS2 to close the M42 and M6 for biggest motorway works yet this summer

Engineers will lift huge bridge structures over two of the West Midlands' busiest motorways across a series of weekend closures starting in late June.

Daniel Forsythe

Transport Correspondent ·

7 min read
Large concrete viaduct under construction above a motorway
Large concrete viaduct under construction above a motorway · Illustrative section image

HS2 is preparing its largest programme of motorway engineering to date, with major operations over the M42 and M6 in the West Midlands taking place across weekend closures between late June and November. The works represent a significant moment for the high-speed rail project, which must thread its new line across some of the most heavily used roads in the region.

The first major operation begins on the evening of Friday 26 June, when engineers install the roof deck of a 300-metre twin-box structure carrying the high-speed line over the M42 near Birmingham Business Park. The work involves placing 175 individual beams, each weighing between 56 and 92 tonnes, in a precisely sequenced lifting operation that can only be carried out when the road below is closed to traffic.

These are among the most technically demanding tasks in the entire construction programme, requiring heavy cranes, exact positioning and tightly choreographed teams working through the night to meet strict deadlines for reopening the carriageways.

Fewer closures than first feared

The campaign was originally expected to require nine weekend closures, but planners have synchronised work on the twin box with the extension of two viaducts near Water Orton, reducing the total to six. A twin-track viaduct will also be installed over the M6 near Chelmsley Wood, adding to the sequence of major lifts scheduled through the autumn.

Combining operations that would otherwise have required separate road closures is intended to limit the cumulative disruption to drivers and to nearby communities. Project managers say bundling the works also improves efficiency on site, allowing specialist crews and equipment to be used more intensively over fewer weekends.

  • First major operation begins on the evening of Friday 26 June over the M42
  • A 300-metre twin-box structure requires 175 beams of 56 to 92 tonnes each
  • A twin-track viaduct will be installed over the M6 near Chelmsley Wood
  • Planning changes cut the number of weekend closures from nine to six
  • Closures run from 9pm Friday to 5am Monday to limit disruption

How disruption will be managed

To limit disruption, junction and motorway closures will run only from 9pm on Friday evenings until 5am on Mondays. Diversion routes will be signposted, and drivers are being urged to plan ahead and allow extra time during affected weekends. The choice of overnight and weekend windows is intended to avoid the heaviest weekday commuter and freight flows on two of the region's most congested routes.

Local businesses and residents have been briefed on the schedule, with project teams emphasising that advance notice and coordination with traffic authorities should keep the impact manageable. Even so, the sheer scale of the lifts means some delay and rerouting is unavoidable for those travelling through the area.

Freight operators and logistics firms, which rely heavily on the M42 and M6 to move goods across the country, have been encouraged to factor the closures into their planning. The West Midlands sits at the heart of the national motorway network, and disruption there can ripple outwards to journeys well beyond the immediate works, making clear communication of dates and diversions especially important.

Installing structures of this size over live motorways is among the most complex work on the route.

An HS2 project spokesperson

Background: a project under scrutiny

HS2 has been one of the most closely watched and frequently debated infrastructure schemes in Britain, dogged by questions over cost, scope and timetable. Against that backdrop, visible construction milestones such as these motorway crossings carry symbolic as well as practical weight, offering tangible evidence of progress on a line that has spent years in planning and earthworks.

The West Midlands sections are central to the project, linking key population centres and requiring the line to cross a dense network of existing road and rail infrastructure. Each successful crossing reduces the remaining engineering risk and moves the route closer to completion.

What happens next

Once complete, traffic will pass through the box structures while high-speed trains run overhead, in what HS2 describes as a major milestone for the new line. Drivers can expect a series of clearly signposted weekend closures through to November, after which the new structures will become a permanent and largely unnoticed part of the motorway landscape. For the project as a whole, completing these crossings marks meaningful progress on one of the most challenging stretches of the route.

Source: This summary is based on reporting by RailBusinessDaily. The NE Times aggregates and rewrites news for readability; please refer to the original for the full report.

For informational purposes only. The NE Times does not provide live or breaking news coverage — we collect stories from established sources and present them in a readable format. Disclaimer.

Share

More from this section

More
HS2 to close the M42 and M6 for biggest motorway works yet this summer | The NE Times